hi Support,
I am using ver 1.7.1 and ext 1.3.1 I have 2 cases :
1. while we open a project and click on the gantt chart directly it is fine we can see that project gantt chart but after we click to project info and then back to gantt chart we can see all projects gantt chart that all we have in one project all mix there, but if we go back to project on the menu and then direct to gantt chart the chart is fine
2. we cannot change the duration on gantt chart , after we save it back to 1 day
please advice
thank you
Gantt Chart mix with other project
- support
- Site Admin
- Posts: 6215
- Joined: 19 Oct 2014, 18:22
- Name: Sergey Kharchishin
- Location: Russia, Evpatoriya
Re: Gantt Chart mix with other project
can you provide screenshots, please?
Re: Gantt Chart mix with other project
hi Support,
here is the screenshot on the attachment for case 1
here is the screenshot on the attachment for case 1
- support
- Site Admin
- Posts: 6215
- Joined: 19 Oct 2014, 18:22
- Name: Sergey Kharchishin
- Location: Russia, Evpatoriya
Re: Gantt Chart mix with other project
Thank you, found this issue (issue in generating url path to gantt chart)
will be fixed in 1.7.2
will be fixed in 1.7.2